Enter the results of a test pass and get both pass rates — of those executed and of those planned — with blocked counted as the unknown it is.
Enter the results of the pass
Five outcomes, not two. Blocked and skipped are different things, and neither is a failure.
Ran, and the result was what the case expected.
Ran, and the result was not what the case expected.
Could not be run because something else was broken. The result is unknown — not a pass and not a failure.
Deliberately not run this time, with a reason. Different from blocked, where you wanted to run it and could not.
Planned and never reached. Each one needs a recorded reason, or the pass cannot be repeated.
Five outcomes rather than two. A blocked case has no result at all — counting it as a failure invents failures, and counting it as a pass is worse.
Enter at least one count to produce a summary.
These are the counts as supplied — nothing here was executed or measured. The summary says so in its own text, because a formatted table of numbers reads as a measurement whatever its source, and someone will quote it in a release decision.
Test Execution Summary runs entirely on your device — the summary is computed in your browser and nothing you enter is sent.
You’re on the Free plan. Compare plans
"Eighty per cent passed" is one of the least informative sentences in software testing, because it does not say eighty per cent of what. Forty of fifty cases run, out of a hundred planned, is an 80% pass rate and 40% of the plan — and reporting only the first number is how a release decision gets made on a figure that was never about the release.
So this reports both: of those executed, which says how the code did, and of those planned, which says how much is actually known. The second is the one that answers whether the pass is finished, and it is the one that usually gets left out.
Blocked is never folded into passed or failed. A blocked case has no result at all — something else was broken and it could not be run. Counting it as a failure invents failures; counting it as a pass is worse. It gets its own column, and skipped gets another, because skipped is a decision and blocked is an obstruction.
Because they answer different questions. Of those executed says how the code performed on the cases that produced a result. Of those planned says how much of the plan is actually known. Forty passes out of fifty run, from a hundred planned, is 80% by the first measure and 40% by the second — and only the second tells you whether the pass is finished.
Because a blocked case has no result. Something else was broken and the case could not be run, so the outcome is unknown rather than negative. Counting it as a failure invents failures that do not exist, and counting it as a pass hides work that has not been done.
Skipped is a decision: not run this time, for a stated reason. Blocked is an obstruction: you wanted to run it and could not. They lead to different next steps, which is why they are counted separately.
No. These are the counts you supply, formatted. The generated summary says so in its own text, because a tidy table of numbers reads as a measurement whatever its source and somebody will quote it in a release decision.
Because a high pass rate over a small fraction of the plan says very little, and it is the most common way a summary gives false confidence. Below about 80% completion the tool says so explicitly.